Visualization of a utility-scale solar plant with a substation and battery storage, as we would build it in Belize and across the Caribbean

Utility-Scale Solar.

Engineered for Caribbean Grids.

Visualization

Utility-scale solar EPC

Utility-scale solar EPC, from first study to grid.

Most of a solar plant’s risk is settled before the first post goes in. In Belize and across the Caribbean, we carry a project from site screening and yield studies through grid studies, permits and lender review to construction, commissioning and decades of operation.

20+MW
In active tenders as of November 2026, with four or more projects in development
8–24+months
To build and commission a plant, from the start of construction. Recent Caribbean plants have been given 12 to 18 months or more
IFC (2015); US EIA with Sargent & Lundy (2024); BEL and BAPCOL (July 2025); Bahamas Power and Light (October 2025); Ministry of Energy and Energy Industries, Trinidad and Tobago (July 2025)
47%
CARICOM’s target for renewable electricity by 2027, from 8% in 2012
CARICOM Secretariat (January 2025); CCREEE (October 2026)
The process

One team, from the first study to the last decade.

Years of development, months of construction, decades of operation. Seven gates decide when a project moves on, and the same team carries it through every one.

01234530+ yearsYears1234567
Develop
Site screening and land
Yield, grid and environmental studies
Licence, consent and clearance
Finance
Power sale: tender or PPA
Lender review to financial close
Build
Design and long-lead orders
Construction
Commission
Tests and acceptance
Operate
Operation and maintenance
Who is involved
Titanium
Utility
Regulators
Lenders and their engineer
  1. 1Site secured
  2. 2Grid study accepted
  3. 3Licence and permits granted
  4. 4Financial close
  5. 5Grid-code tests passed
  6. 6Commercial operation
  7. 7Final acceptance
Source and notes
An illustration of the usual order; durations vary widely from project to project. For a 150 MW plant, the US EIA and Sargent & Lundy allow 24 months of development, permitting and engineering, then 12 months of construction (January 2024). In US data, plants built in 2025 waited a median of over five years from grid request to operation: Lawrence Berkeley National Laboratory, Queued Up (2026).
  1. 01

    Develop

    • Site screening, land and concept layout
    • P50/P90 energy yield report
    • Grid studies with the utility
    • Environmental and social assessment
    • Licence, permits and environmental approval
  2. 02

    Finance

    • Power purchase agreement with the utility
    • Lender and technical review
    • Financial close
  3. 03

    Build

    • Detailed design, signed by licensed engineers
    • Protection settings and plant controls
    • Long-lead orders, shipping and customs
    • Civil works, piling and structures
    • Substation, cabling and storage
  4. 04

    Commission

    • Grid-code and performance tests
    • Capacity test
    • Acceptance and handover
  5. 05

    Operate

    • Monitoring to IEC 61724-1
    • Maintenance and annual reporting
    • Repowering and end-of-life plan
Across the Caribbean

Caribbean grids are buying solar with storage.

Utilities, regulators and governments across the region are tendering utility-scale solar, and more of them now ask for batteries with it. A selection of current projects and tenders, each from the body that published it.

Solar or renewables, MWBatteries, MW
  1. Puerto Rico
    Contracts before the Energy Bureau
    Reviewed, March 2026
  2. Dominican Republic
    Renewables awarded by CUED
    Awarded, June 2026
  3. Jamaica
    Generation Procurement Entity tender
    Tender, May 2026
  4. Belize
    Utility-scale solar tender, with IFC
    Five bidders prequalified, August 2026
  5. Barbados
    Ministry of Energy and Business tender
    Tender, 2026
  6. Guyana
    GUYSOL, eight solar farms
    Five of eight farms operating, January 2026
  7. Cayman Islands
    Regulator’s solar and battery tender
    Bids under evaluation since 2025
  8. Bahamas
    Baillou Hills, New Providence
    Due early 2027
Source and notes
Puerto Rico Energy Bureau, Resolution and Order NEPR-MI-2025-0005 (March 2026). CUED, Dominican Republic (24 June 2026). Jamaica Information Service (6 May 2026). Belize Electricity Limited, RFQ (January 2026) and prequalification notice (August 2026). Ministry of Energy and Business, Barbados, RFP (2026). Guyana Power and Light, GUYSOL (read November 2026); Department of Public Information, Guyana (19 January 2026). Utility Regulation and Competition Office, Cayman Islands (July 2025) and its 2026 Annual Plan (December 2025). Bahamas Power and Light (October 2025).
Site and permits

Most sites fail on paper.

We screen sites out before money is spent on them: protected land, flood and wildfire risk, land title, archaeology and the route to a substation. When Belize screened land for its 80 MW tender with IFC, six of 26 sites made the shortlist.

Visualization of two surveyors on open pasture, one with a GPS survey pole and one flying a mapping drone, beside a line of flagged survey stakes
Visualization
  1. 26

    Sites reviewed on environmental, social, heritage and biodiversity criteria, with GIS, field visits and local input

  2. 6

    Shortlisted, all in northern Belize, for final grid, survey and soil studies

  3. 4

    Up to four selected to host the 80 MW of solar

Sale, licence and approval.

Every grid in the region buys power, licenses plants and approves sites its own way. The lenders bring one standard that applies everywhere.

Power sale
A power purchase agreement with the utility, often won in a tender. Jamaica’s Generation Procurement Entity, the Cayman Islands’ regulator and Belize’s utility, with IFC, have each run one since 2025.
Licence
Each grid has its own route. In Belize, a plant that sells to the utility is licensed by the PUC as an independent power producer and needs a separate consent to build.
Environment
An approval scaled to the plant. In Belize: a clearance under 10 MW, a limited study up to 30 MW, and a full impact assessment above 30 MW or 200 acres.
Lenders
IFC Performance Standards 1 to 8 and the Equator Principles: impact assessment, a management plan, community engagement and a grievance mechanism.
Source and notes

Belize Solar PV Project, up to 80 MW: project teaser, Government of Belize, BEL and IFC, January 2026. Screening by IFC and its environmental and technical consultants. Their process, shown as an example.

Jamaica Information Service (May 2026); Utility Regulation and Competition Office, Cayman Islands (July 2025); BEL RFQ (January 2026). Belize: Electricity Licensing and Consent Regulations, S.I. 47 of 2026; Environmental Impact Assessment Regulations, S.I. 97 of 2026. IFC Performance Standards (2012); Equator Principles (EP4, 2020).

Energy yield

Bankable numbers, not best guesses.

Investors most often require a P90 yield: the energy a plant should beat nine years in ten. It is built from decades of satellite data and a model of the plant, carried out or reviewed by an independent specialist.

Sun across the Caribbean.

From Nassau to Port of Spain, the sun averages 5.1 to 5.8 kWh/m² a day. Each site’s dullest year since 1984 came in 6 to 10% below its own average.

4.55.05.56.0Avg
  1. Nassau, Bahamas5.2
  2. Grand Cayman5.5
  3. Northern Belize5.1
  4. Kingston, Jamaica5.5
  5. Santo Domingo5.5
  6. San Juan, Puerto Rico5.2
  7. Guadeloupe5.5
  8. Bridgetown, Barbados5.7
  9. Willemstad, Curaçao5.8
  10. Port of Spain, Trinidad5.2
Average, 1984–2024Dullest to brightest yearDullest yearkWh/m² a day

From P50 to P90.

Add the uncertainty of the data and the model, 8 to 10% in all, and the P90 sits 1.28 standard deviations below the middle estimate. At 8%, that is about 90% of P50.

P50Middle estimateP9090% of P50Lower yieldHigher yield
Source and notes
Sun: NASA POWER, annual all-sky irradiance at ten sites, 1984–2024; ERA5 via Open-Meteo (1990–2024) gives similar averages. Uncertainty and P90: IFC, Project Developer’s Guide (2015); PVsyst, P50–P90 evaluations.
Grid and storage

Designed for small grids.

On a small grid a solar plant has to behave like a power station: ride through faults, hold voltage, answer frequency changes and limit how fast its output moves when clouds pass. A plant controller and batteries do that work.

Visualization of a large solar plant from the air, in blocks divided by gravel roads, with a fenced substation at one corner, among farmland and forest
Visualization
  • Solar output
  • To the grid, ramp-limited
  • Battery fills or absorbs the gap
100%50%0
10:0011:0012:0013:00

Plant output, % of capacity

What a utility plant needs.

Grid studies with the utility: power flow, short circuit and stability. A plant controller that holds voltage and ramp rate at the point of connection. SCADA on open protocols such as IEC 61850 and DNP3, secured to IEC 62443. Grid-code conformity shown by test and model, as IEEE 2800.2 sets out, and batteries to UL 9540 and NFPA 855.

How the region asks for it.

Puerto Rico
Output may change by no more than 10% of capacity a minute, frequency response must come within one second, and batteries are a named way to comply.
Jamaica
Solar and wind plants must hold voltage at the connection point and supply resource forecasts to the system operator.
Barbados
A 60 MW, 240 MWh battery tender, because “storage or curtailment is needed to avoid Public Grid stability issues”.
Show 2 more
Cayman Islands
The regulator’s 22.5 MW solar tender comes with batteries, so the power can be dispatched at peak.
Belize
The utility’s published connection rules cover 22 kV and below; in April 2026 the regulator said it expected transmission and distribution codes by the end of 2026.
Source and notes

Illustration: a passing-cloud morning in one-minute steps. The ramp limit, 10% of plant capacity a minute, is from Puerto Rico’s minimum technical requirements for solar plants.

FERC pro forma interconnection procedures, sections 6.2 and 7.3. Standards bodies’ own pages, read November 2026.

PREPA, Minimum Technical Requirements for PV (2024 RFP). Office of Utilities Regulation, Jamaica, Electricity Book of Codes (2016). Ministry of Energy and Business, Barbados, RFP (2026). Utility Regulation and Competition Office, Cayman Islands (July 2025). BEL interconnection requirements (2023); PUC Belize (April 2026).

Finance and contracts

Built to pass a lender’s review.

Utility plants are most often project-financed, so the lenders and their engineer check the project before they lend and before each release of funds. We prepare for that review from the first study.

Project company
Owns the plant; every contract runs to it
RegulatorsEnergy and environment
Licences, permits, approvals
UtilityBuys the power
Power purchase agreement
Lenders’ engineerIndependent review
Yield, design, contracts
OwnersEquity investors
Equity
TitaniumDesign, build, operate
EPC and O&M contracts
LendersBanks and development banks
Loan

What the lenders’ engineer checks.

Energy yield
A bank-grade P50 and P90, carried out or reviewed by an independent specialist
Design
Single-line diagrams, layout, structure and the grid connection
Equipment
Makers on lenders’ bankability lists, with independent test results
Contracts
Damages for delay and performance, a performance-ratio guarantee, a defects warranty of at least two years and a performance bond
Environment
IFC Performance Standards and the Equator Principles
Construction
Certificates of progress before each release of funds
Source and notes
IFC, Project Developer’s Guide (2015); PV Evolution Labs, Scorecard methodology (2026); IFC Performance Standards (2012); Equator Principles (EP4, 2020).
Procure and build

Ordered early, built for the storm.

The largest electrical parts can take longer to arrive than the plant takes to build, so they are ordered early. On site, the structure is designed above the code minimum for Caribbean hurricanes.

Visualization of two installers bolting solar modules to a single-post table, its post and two braces between them, with a pile-driving rig setting the next posts behind
Visualization
Generator step-up transformer
143 weeks
Power transformer
128 weeks
Switchgear
44 weeks
Building a 150 MW plant
52 weeks

What the storms taught.

On St Croix, arrays designed to code failed at about 104 mph against a design wind of 145 mph. Hurricane Maria did extensive damage to the second phase of Puerto Rico’s Humacao solar farm while it was being built. Beryl damaged about 30% of the panels at Union Island’s solar farm, and Melissa, at 185 mph, did catastrophic damage to Jamaica’s 52 MWp Eight Rivers solar park.

How we build against it.

We design above the code minimum, with the practices RMI found held up after Beryl: through-bolted modules, lateral racking support and vibration-resistant connections, on one post as standard, or two where the site’s wind or soil calls for it. Racking, foundations and corrosion are set out in our ground-mount build details.

Source and notes

Average lead times after order, US market, Q2 2025: Wood Mackenzie (September 2025). Build time for a 150 MW plant: US EIA with Sargent & Lundy (January 2024).

US DOE FEMP with NREL and LBNL, St Croix (February 2023). PREPA, IRP 2019 Appendix 3 (December 2018). CDEMA, Situation Report 2, Hurricane Beryl (3 July 2024; preliminary). NOAA National Hurricane Center (28 October 2025). InterEnergy (8 November 2025). RMI, Solar Under Storm III (2025).

Handover and operation

Proven before handover, run for decades.

Every string is tested, the grid-code tests are passed and the plant’s capacity is proven before it is accepted. Then the work is keeping it close to its first-year output for thirty years or more.

Visualization of a technician at the end of a row of single-post solar tables, flying a thermal-camera drone and watching the thermal image on the controller
Visualization
100%90%80%12345Median 0.5% less a year
Year 0Year 10Year 20Year 30

Output, % of the first year (axis starts at 75%)

  1. 1Commercial operation, once every test is passed
  2. 2Final acceptance, after a defects warranty of at least two years
  3. 3Inverters replaced or refurbished, once or twice
  4. 4Module power warranties end, at 25 or 30 years
  5. 5Repower, or decommission and recycle

What we hand over.

  • As-built drawings and single-line diagram
  • String test records to IEC 62446-1
  • Infrared survey to IEC TS 62446-3
  • Grid-code and protection test results
  • Capacity test report (ASTM E2848 or IEC TS 61724-2)
  • Monitoring set-up to IEC 61724-1
  • O&M manual, warranty and spares register
Operation and maintenance
Source and notes
Degradation: NREL, Jordan and Kurtz (2013; median 0.5% a year). Defects warranty and inverters: IFC (2015). Module warranties and plant life: LBNL (2020), 17 of 19 organizations assume 30 years or more. Recycling: EU WEEE Directive 2012/19/EU (85% recovery, 80% recycling for panels). Tests: IEC 62446-1, IEC TS 62446-3, IEC 61724-1, ASTM E2848.
Questions

What developers ask us.

How long does a utility-scale plant take?

Building and commissioning takes about 8 months to 2 years or more from the start of construction; recent Caribbean plants have been given 12 to 18 months or more. Development comes first: about two years for a 150 MW plant in the US EIA’s cost study. The grid connection can take longer still: in US data, plants built in 2025 waited a median of over five years from grid request to operation (LBNL).

Who buys the power?

Usually the national or island utility, under a power purchase agreement, often won in a tender. Jamaica’s Generation Procurement Entity, the Cayman Islands’ regulator and Belize’s utility, with IFC, have each run solar tenders since 2025.

Does a utility plant need storage?

More and more often. Jamaica’s 2026 tender pairs 300 MW of renewables with 150 MW of batteries, the Cayman Islands’ 22.5 MW solar tender comes with batteries, and Puerto Rico’s grid rules name storage as a way to meet its ramp and frequency limits.

What is P90?

The yearly energy a plant should beat nine years in ten. It sits 1.28 standard deviations of the combined uncertainty, typically 8 to 10%, below the P50, the middle estimate. Investors most often require it.

Who checks the work for the lenders?

The lenders’ engineer. Before construction the design and yield are reviewed independently; during construction the lenders’ engineer issues certificates of progress, and lenders release funds against them.

What happens at the end of a plant’s life?

Inverters are replaced or refurbished once or twice along the way. After thirty years or more, the owner repowers, or decommissions and recycles. EU law already sets 85% recovery for solar panels.

Local Expertise

Navigating Belize’s Energy Landscape

Belize’s energy rules are changing fast. Our engineers are fully licensed, and our established partnerships keep each project in step with every change, so our clients’ projects are delivered with ease.

  • PUC Licensed

    Titanium Energy’s engineers are fully licensed by the Public Utilities Commission. Every system we build meets Belize’s grid and safety requirements as they stand today.

  • PUC Collaboration

    We work directly with the PUC from feasibility studies to final interconnection approval, so each new rule is part of our clients’ projects from the start.

  • BTB Partnership

    For resort and tourism projects, we coordinate closely with the Belize Tourism Board to align each installation with tourism development and national sustainability priorities.

  • Cross-Agency Coordination

    Our working relationships with the energy ministry, the environment and lands departments and municipal authorities keep permits moving as the rules change.

“For foreign investors and developers, navigating Belize’s regulatory environment can be the biggest project risk. Our established relationships turn that risk into a managed process.”

Jakob WoodruffCEO
Start here

Send us your project.

Five facts are enough for a first answer: what the site can carry, which route to market fits, and what to study first.

  1. 01Where the land is, and how much
  2. 02The size in mind, in MW, and any storage
  3. 03Who buys the power: a utility tender, a PPA or your own use
  4. 04What’s done: land, studies, a grid request
  5. 05Your timeline and how you plan to finance it